How are changes to the website scope priced and approved?
Webgate team · 1 min read
Quick answer
Compare the request with the approved scope, then agree on its effect on cost and timing before work starts. A useful change request records the requested outcome, the estimate, the approver and the impact on the launch plan.
An example from a demo form
Changing a label during an agreed review round may fit the original scope. Adding country-based sales assignment introduces new CRM rules and test cases, even if the form looks identical.
Ask whether the change can replace a lower-priority item, move into a later release or receive a separate budget. Record the choice alongside the original acceptance criteria.